Add new field on shift turnover report, seperate reduced time and downtime
Is there a way to separate DT & reduced time into different fields. I recently became aware our shift turnover report is reporting inaccurate data regarding true DT. Most of our people tracking DT will do so using a shift turnover report, I recently came across TaskID 6396664 for site 727, where they have a reduced ticket showing 543hrs of DT. As far as cost savings goes, this can defeat any savings potential we have for this project. We need to truly differentiate DT and Reduced time.
1
vote