Period Capacity technician assignment
Ability to assign to technician from Period Capacity – Drop down with tech names and available dates
Based on the WEM process, the Period Capacity and Daily Capacity screens represent two discrete functions. Scheduling tasks to a period should not be technician specific, as we are scheduling to a specific skillset prior to bringing in technician availability.
-
Thornton, Nicholas D. commented
If assigned form the Period Capacity ideally this would schedule for week completed and is automatically moved to the Daily Capacity. It would not sit in Period capacity
-
When we schedule weekly, we want to do this based on the skills required to complete that task. We do this because these tasks in the period capacity are our "Ready Backlog." We don't want our Ready Backlog to be technician specific.