Current week available for planning OT.
Current week should be available to plan tasks for non assigned work days, example we work M-Th, OT is Friday and Saturday. These jobs on OT are often Priority 3 tasks that the customer request completed on Non production hours.
3
votes
Nathan Arbuckle
shared this idea
Per Bill Sparling, scheduling by period should only be done for future weeks. The Daily Capacity screen can be utilized for scheduling break-in work (Priority 1 or 2) in the current week. Please contact Operations Excellence with any questions on this process.