PM Schedule Rules
There needs to be 12 WEEK, 24 WEEK and 48 WEEK PM schedule rules to match 4 WEEK. This allows for PMs to be scheduled to land on the exact same day of the week every time they generate. This makes is significantly simpler to schedule these PMs with the customer and minimizes downtime as the asset only needs to be down once for each PM event instead of multiple times. This allows a cadence to be established with the customer for equipment availability on a consistent basis. The most important benefit is that it allows for level loading of PM schedules week to week and month to month.
-
Hayden, Michael commented
This is a critical component for the sites to load level PMs and align with our customers needs and work together to achieve a strong, reliable relationship.
-
Gabriela Belmares commented
Favor de agregar esta plantilla en el EFP3.0. Gracias
-
Moreno, Emmanuel commented
As a necessity of the customer the site 015 needs a 10 months PM rule
-
dfaust commented
Or maybe even a "Custom" selection. It could allow you to add that schedule that fits odd production schedules. Don't know if its feasible.
-
Christopher Atchison commented
We have many customers that have specific shutdown days, that are on a set calendar.
The current Site that I am supporting, shuts down 1 production line every Friday for 8 weeks to cover their 8 production lines, and then the cycle starts over.
If bi-monthly is used, there is a 1 week gap between the end of the 8 weeks and the start of another.
Therefore, I need an "8 Week" interval that I can select as a scheduling option.